FILLING THE DOMESTIC HOT WATER AND
HEATING CIRCUITS (see illustrations B, G et H)
IMPORTANT
The hot water tank must be pressurised before the
heating circuit is filled.
1. Fill the domestic hot water circuit and bring it up to pressure.
2. Fill the heating circuit taking care not to exceed the 2 bar
pressure limit.
3. Vent the air from the top of the boiler.
4. After venting the air from the system, bring the pressure up to
the static head plus 0.5 bar: 1.5 bar = 10m -2 bar = 15 m.
5. Check the power connection, the boiler room ventilation, and
ensure that there are no leaks in the flue gas discharge pipes.
6. Set the boiler thermostat to between 60 and 90 °C.
7. Set the Summer/Winter selector to the desired position.
8. Switch the on/off switch to the ON position.
9. Check the oil supply
(and return).
10. Carry out the required venting, measurement and setting
procedures.
STARTING ACV BMV1 AND BMV2 BURNERS
Refer to the ACV BMV1 and BMV2 burner manual supplied with them.
RECOMMENDATION
ACV advises that boilers should be serviced at least once a year.
The burner must be serviced and tested by a competent engineer.
SERVICING THE BOILER (see illustration K)
1. Switch off the power at the mains switch outside the boiler and
shut off the oil supply.
2. Set the on/off switch on the control panel to the OFF position.
3. Remove the top cover of the boiler (2) and take off the top of the
chimney reduction (3).
5. Remove the turbulators (23) from the flue pipes (22) for cleaning.
Change them if in poor condition.
6. Unscrew the burner chamber plate (10).
7. Brush the flue pipes (22).
8. Clean the burner chamber (18) and the burner.
9. Check the condition of the burner chamber plate insulation.
SERVICING THE SAFETY DEVICES
- Check that all thermostats and safety devices are working
properly : boiler thermostat, cut-off thermostat and manually reset
safety thermostat.
-Test the safety valves on the central heating and hot water circuits.
SERVICING THE BURNER
Refer to the ACV BMV1 and BMV2 burner manual supplied with them.
EMPTYING THE BOILER
Water flowing out of the drain cock is extremely
hot and can cause severe burns.
Keep people away from discharges of hot water.
Emptying the heating circuit (see illustration G)
1. Set the on/off switch on the control panel to the OFF position,
turn off the power at the external mains switch and close the oil
feed valve.
2. Close the isolating valves (8).
3. Connect a hose to the drain cock (9).
4. Open the drain cock to empty the primary circuit.
Emptying the hot water circuit (see illustration H)
1. Set the on/off switch on the control panel to the OFF position,
turn off the power at the external mains switch and close the oil
feed valve.
2. Lower the pressure in the heating circuit until the pressure
gauge indicates zero bar.
3. Close the valves (7 and 11).
4. Open valves (9) and (10) (first 9 then 10).
5. Let the water empty into the drain .
For the tank to be emptied, valve (9) must be situated
at ground level.
SERVICINGSTARTUP
16

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln
1

Forum

acv-delta-performance-ventouse-fv

Suche zurücksetzen

  • Hallo,
    wir benötigen eine Anleitung zum Anschluß eines Außenfühlers für die
    ACV Delts Performance 25 Baujahr 2008.
    Können Sie uns behilflich sein?
    mfG
    Pius Lochbruner Eingereicht am 3-1-2022 09:02

    Antworten Frage melden
  • Hallo,
    wir haben eine Delta Ferformance 25 Baujahr 2008.
    Gibt es hierzu noch eine Bedienungsanleitung? Es geht um den
    Anschluß eines Außenfühlers.

    Vielen Dank.
    Eingereicht am 3-1-2022 08:48

    Antworten Frage melden

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für ACV Delta Performance ventouse FV wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info