Protect PV.250 Operating Instructions
Page 13 of 51 80000027023 BAL, en
If the DC voltage continues to increase due to the sun's rays get-
ting stronger and the mains voltage and mains frequency are
within acceptable limits, a start-up attempt is made. During a start-
up attempt, the inverter stack is switched on, thereby drawing
power from the DC voltage that is present. The inverter output con-
tactor is open during a start-up attempt. If the load on the DC volt-
age causes it to collapse too dramatically during this start-up at-
tempt, the stack is switched off again and there is a delay until the
next start-up attempt is made. If the DC voltage does not dip too
significantly, the inverter output contactor closes and power is fed
into the mains. The inverter is now in the "Operation" status.
Day:
During the course of the day, the inverter will remain in the "Opera-
tion" status if the sun's rays are strong enough and no faults occur.
Power is fed into the mains and the inverter output contactor K7 is
closed.
Evening:
As the sun goes down, the power fed into the mains decreases. If
this power falls below a certain value for a certain time, the operat-
ing conditions are no longer met. The inverter stack is switched off,
the inverter output contactor K7 opens and the unit switches to the
"Waiting" status.
Once the "Waiting" status delay has elapsed, the unit switches
back to "Waiting for feed conditions". Although the sun's rays are
not as strong, the DC voltage might still be high enough for a suc-
cessful start-up attempt with the inverter stack and the inverter
output contactor K7 being switched on again. However, because
the sun's rays are not as strong, it is unlikely that the operating
conditions will still be met in the "Operation" status. As a result, the
unit will switch back to the "Waiting" status once a delay has
elapsed. When the unit switches back to this status, the delay is
extended until the unit switches back to the "Waiting for feed con-
ditions" status.
The cyclic changes of status "Operation" -> "Waiting" -> "Waiting
for feed conditions" -> "Operation" can take place several times
depending on insolation, the time of year, location and other condi-
tions (e.g. snow on the PV cells). So that the inverter output con-
tactor K7 is not overloaded by this cycle of changes, the delay in
the "Waiting" status is extended every time the unit switches to this
status.
This has very little effect on the energy fed in, because the low
levels of insolation mean that hardly any energy is being gener-
ated.
Later in the evening:
Levels of insolation continue to fall. As a result, the DC voltage
drops again. If the DC voltage drops below a certain value for a
certain time, no more start-up attempts are made. If the DC volt-
age continues to drop, the unit switches to the "Night" status.
Night:
The Protect PV.250 shuts down all possible loads so that as little
energy as possible is being consumed. The inverter remains in the
"Night" status until the following morning.
13

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für AEG Protect PV 250 wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Andere Handbücher von AEG Protect PV 250

AEG Protect PV 250 Bedienungsanleitung - Deutsch - 52 seiten


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info