7 Commissioning
Logano plus GB402 – 6 720 804 428 (2012/09)
21
Fig. 25 Gas connection
[1] Anti vibration connection
[2] Gas isolation valve (here with thermally activated shut-off
equipment)
[3] Pipe clip
7 Commissioning
This Chapter describes commissioning using the standard control unit
module.
After completing the work described below, complete the
commissioning report ( Chapter 7.18, page 28).
Never operate the boiler when there is a lot of dust, e.g. due to
building work. Never install air filters in the inlet path if there is a high
dust load. Convert the boiler to balanced flue operation if the dust
loads are excessive.
Burners contaminated during building work must be cleaned before
commissioning.
Inspect flue and combustion air pipework (with balanced flue
operation) and the apertures for combustion air supply and
ventilation ( Chapter 6.1, page 13).
7.1 Checking the operating pressure
Prior to commissioning, check the operating pressure of the heating
system on the water side and adjust if required.
Set the red needle [1] of the pressure gauge to the required operating
pressure of at least 1bar.
Fig. 26 Pressure gauge for sealed unvented systems
[1] Red needle
[2] Pressure gauge needle
[3] Green marking
Top up heating water or drain off water via the on-site drain & fill valve
until the required operating pressure has been reached.
During filling, vent the heating system via the radiator bleed valves.
7.2 Checking for leaks
Prior to commissioning, check all new line sections on the gas side for
external gas tightness.
For higher gas supply pressures than shown in Tab. 11,
( page 24), Buderus offers additional gas pressure
regulators as accessories.
NOTICE: Boiler damage through excessive dust and dirt
contamination in open flue mode!
Strong dust and dirt contamination can occur, for
example, due to building work in the installation room.
During building work, operate the boiler in balanced
flue mode.
NOTICE: Risk of boiler damage through contaminated
combustion air.
Never use chlorinated cleaning agents or halogenated
hydrocarbons (as contained in spray cans, solvents,
cleaning agents, paints and adhesives, for example).
Never store or use such substances in the installation
room.
This boiler cannot be operated with open vented heating
systems.
NOTICE: System damage through boiler scaling!
Note the information specified in the operator's log.
CAUTION: Health risk through contaminated drinking
water.
Always observe the regulations and standards
applicable in your jurisdiction for the prevention of
contamination of drinking water (e.g. by water from
heating systems).
In Europe, observe standard EN 1717.
DANGER: Risk of explosion!
There is a risk of explosion if gas lines and gas
connections leak.
Carry out an appropriate tightness test using
appropriate means.
DANGER: Risk of system damage due to short circuit!
Cover the areas at risk before performing a tightness
test, e.g. the internal water pressure sensor and the
return sensor on the boiler return.
Never spray or let leak detection agent drip onto cable
entries, plugs or electrical cables/leads.
6 720 615 876-59.1RS
3
2
1
21

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für Buderus Logano plus GB402 wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Andere Handbücher von Buderus Logano plus GB402

Buderus Logano plus GB402 Bedienungsanleitung - Deutsch - 2 seiten

Buderus Logano plus GB402 Bedienungsanleitung - Englisch - 20 seiten

Buderus Logano plus GB402 Installationsanweisung - Holländisch - 60 seiten

Buderus Logano plus GB402 Bedienungsanleitung - Holländisch - 16 seiten


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info