Commissioning and shutting down
MCM10
67
4 Commissioning and shutting down
4.1 Configuration
With this configuration, the control characteristics of the
MCM10 master module are adapted to the specific
heating system.
The MCM10 module is configured automatically:
when commissioning a MCM10 module,
during a restart following a reset of the configuration
(Æ chapter 4.3).
Wait 5 minutes until the configuration has been
completed. During configuration, the LEDs associated
with the connected boilers and possibly the LED to
indicate BUS communication (Æ tab. 10, page 68) flash.
Configuration is completed and saved to the MCM10
when no more LEDs are flashing.
Any configuration saved remains in the memory, even in
case of power failure.
If, after configuration, a boiler (or a MCM10 module) is
temporarily shut down during active operation (e.g. for
maintenance), the LED assigned to that boiler or the
LED to indicate BUS communication begins to flash.
Following a restart, the boiler (or MCM10 module) will be
recognised, and the associated LED stops flashing.
4.2 Commissioning
B Ensure the correct connection of all heating system
components.
B Provide the power supply (230 V AC) for all
components of the heating system, except for
MCM10 modules.
B Start all boilers (switch ON).
B Provide the power supply via the mains plug of the
(first) MCM10 module.
Configuration commences. Wait 5 minutes until the
configuration has been completed.
B Make the necessary adjustments on the individual BUS
subscribers in accordance with their installation
instructions.
4.3 Configuration reset
During the next start, the current system configuration is
saved to the MCM10 module.
B Interrupt the power supply (230 V AC) to all
components in the heating system and all MCM10
modules.
B Open the MCM10 master module casing (Æ fig. 7,
page 64).
B Remove jumper (Æ fig. 4, page 63).
B Ensure the correct connection of all heating system
components.
B Provide power (230 V AC) to all components of the
heating system, except for MCM10 modules.
B Start all boilers (switch ON).
B Provide the power supply to the MCM10 master
module.
B To prevent fault functions: with system versions 2 or 3,
ensure that the jumper is inserted at the correct
position.
B Refit jumper (Æ fig. 4, page 63).
Configuration starts. Wait 5 minutes until the
configuration has been completed.
B Close MCM10 module casing.
4.4 Shutting down
B Interrupt the power supply to all MCM10 modules and
all boilers.
Troubleshooting in case of faults becomes
more difficult if the saved configuration does
not match the actual configuration of the
heating system.
B Implement a configuration reset after any
intended/remaining modification of the
system configuration (Æ chapter 4.3), to
enable the new system configuration to be
saved in the MCM10 master module.
The cascade configuration is set at the
MCM10 module during commissioning or
after a reset (Æ chapter 4.1).
B Monitor the LEDs during configuration to
detect lead/cable breaks or wiring faults.
The heating system configuration is saved in
the MCM10 master module. Resetting the
MCM10 master module deletes the
configuration of all MCM10 modules.
67

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für Buderus MCM10 wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info