7.4 Leak test and evacuation
Air and moisture in the cooling system have unwanted effects
as outlined below.
1) The pressure in the system increases.
2) The operating current increases.
3) The cooling (or heating) output falls.
4) Moisture in the cooling circuit can freeze and block the
capillary tubes.
5) Water can cause corrosion on parts in the cooling
system.
This means that the indoor and outdoor unit, as well as the con-
nection pipe, must be checked for leaks and pumped empty to
remove any non-condensable gases and moisture from the
system.
7.4.1 Preparation
Ensure that each pipe (liquid and air side) between the indoor
and outdoor unit is connected correctly and the wiring for the
test operation has been carried out. Remove the maintenance
valve caps from both the gas and liquid side of the outdoor unit.
Ensure that both maintenance valves on the liquid and air side
of the outdoor unit are closed at this point.
7.4.2 Leak test
Connect the multi-way valve (with pressure gauges) and
dry nitrogen gas cylinder with the filling hoses on this
maintenance connection.
NOTE
º
ºººº
A multi-way valve must be used for the leak test. If no multi-
way valve is available, an isolating valve can also be used. The
"Hi" lever on the 3-way valve must be closed at all times.
The system may be charged with max. 3.0 MPa dry nitro-
gen. The cylinder valve must be closed with a pressure of
3.0 MPa. The next step is to search for leaks with liquid
soap.
NOTE
º
ºººº
In order to prevent liquid nitrogen from entering the cooling
system, the top side of the gas cylinder must be higher than
the bottom side when pressure is building in the system.
1) The gas cylinder is usually used in an upright position.
Check all pipe connections (indoor and outdoor) and main-
tenance valves of the air and liquid side for leaks. Bubbles
indicate a leak. The soap must be wiped away with a clean
cloth.
2) If no leaks are identified in the system, reduce the nitrogen
pressure by removing the filling hose connection from the
gas cylinder. When the system pressure is normal again,
the hose must be removed from the gas cylinder.
7.4.3 Evacuation
1) Connect the end of the filling hose mentioned above to the
vacuum pump to pump the pipework and indoor unit
empty. The levers "Lo" and "Hi" on the multi-way valve
must be open. Start the vacuum pump. The duration of the
pumping empty process varies with different lengths of
the pipework and the pump output. The following table
shows the time required for pumping empty.
2) Close the levers "Lo" and "Hi" on the multi-way valve at the
desired vacuum pressure and switch off the vacuum
pump.
Finally
1) Open the valve handle on the liquid side completely in an
anti-clockwise direction with a maintenance valve key.
2) Open the handle of the valve on the gas side completely in
an anti-clockwise direction.
3) Loosen the filling hose connected to the air side slightly
from the maintenance connection to reduce the pressure,
then remove the hose.
4) Tighten the screw nuts and caps on the air side mainte-
nance connection again with an adjustment key. This pro-
cess is very important to prevent leaks on the system.
5) Position the valve caps on the air and liquid side mainte-
nance valves again and tighten. The purging with the vac-
uum pump is complete. The split-heat pump is now ready
for test operation.
A siphon prevents water from entering the electrics
Adhesive tape
Drain hose
(not used)
Refrigerant pipes
Connection cable
Mains cable
KlebebandKlebebandAdhesive tape
opening around opening around
the pipings with the pipings with
gum type sealer.gum type sealer.
Seal small gaps
around the pipe,
e.g. with silicon.
Siphon
TrapSiphon
Seal a small opening Seal a small opening
around the pipings
around the pipings
with gum type sealer.
with gum type sealer.
Seal small gaps around
the pipe, e.g. with silicon.
Time required for pumping empty with a
0.11m_/hour vacuum pump
Length of the pipework
less than 10 m
Length of the pipework
more than 10 m
30 min. or longer 60 min. or longer
0.6 mbar or less
39

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für Dimplex LAK 14IMR wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info