In order for operator to be familiar enough with measurements in and their typical
applications in IT supply system it is advisable to read Metrel handbook Measurements
on IT power supply systems.
B.1 Standard references
EN 60364-4-41, EN 60364-6, EN 60364-7-710, BS 7671
B.2 Fundamentals
IT supply system is mains supply system that is insulated from ground (PE) – it is
ungrounded supplying system. The system is without direct connection to the ground or
the connection is provided through relatively high impedance. It is applied mostly in
areas where additional protection to electric shock is required. Typical places are
medical surgery rooms.
IT supply system also omits any grounding currents except leakages, and in this way
there aren’t problems with step voltage, i.e. voltage drop in one step, neither high
energy sparking in Ex areas.
In normal cases the high impedance to the ground exists and is formed by capacitances
of supply wires to the ground plus capacitances between primary and secondary
windings of IT supply transformer. Minor part is formed by Y capacitors (EMC) in mains
section of connected equipment. Selecting appropriate transformer, installation cabling
and selection of optional high impedance connection to ground can control maximum
leakage current.
Depending on application area additional impedance to the ground can be applied as
presented in figure D.1 or through special loading equipment. Value of the impedance
should begin from 100 Ω.
IT system represents additional level of protection to electric shock. In the case of a
failure of any line insulation to the PE through equipment failure, wrong application or
procedure, this system is still safe but converted to TN / TT type. However, additional
failure is hazardous, which means that the insulation has to be continuously checked
and repaired immediately after detected failure.
Supplementary to other protection devices the IT system normally contains insulation
monitoring device (IMD) or system that alarms when insulation resistance or impedance
is below set threshold. Threshold value depends on environment. Typical value for
medical installations is 55 kΩ.
In some countries it is not enough to trace insulation resistance of IT supply system to
the ground, they require tracing of system capacitance, too.
IEC 60364-4-41 (©IEC): In IT systems live parts shall be insulated from earth or
connected to earth through sufficiently high impedance. This connection may be made
either at the neutral point or at midpoint of the system or at an artificial neutral point.
The latter may be connected directly to earth if the resulting impedance to earth is
89

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für Metrel MI 3102 BT - Eurotest XE wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Andere Handbücher von Metrel MI 3102 BT - Eurotest XE

Metrel MI 3102 BT - Eurotest XE Bedienungsanleitung - Holländisch - 33 seiten


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info