8.3.2 New installation work (when using new refrigerant piping)
(1) Air purge by vacuum pump and gas leakage inspection (see Fig. 6)
a) Connect the charge hose to the outdoor unit. 1
b) Connect the charge hose to the vacuum pump adapter. 2
At this time, keep the control valves in the fully closed position. 3 4
c) Place the handle Lo in the fully opened position 5, and turn on the vacuum pump’s power switch.
During this step, perform evacuating (about 10 ~ 15 minutes); for the evacuating time, refer to the equipment manufacturer’s
manual.
d) When the compound gauge’s pointer has indicated -0.1 MPa (-76 cmHg) 6, place the handle Lo in the fully closed position 5,
and turn OFF the vacuum pump’s power switch
Keep this state for 1~2 minutes, and ascertain that the compound gauge’s pointer does not return.
e) Fully open the control valves. 3 4
f) Detach the charge hoses. 1 2
g) Tightly secure the cap on the service port. 7
h) After securing the caps on the control valves, check the caps’ periphery if there is any gas leakage. 3 4 7
(2) Additional refrigerant charging required for refrigerant piping length longer than standard length (The following steps should be
taken following the step e) in (1) above. See Fig. 7)
a) Set the refrigerant cylinder to the electronic balance, and connect the connecting hoses on the cylinder and electronic balance’s
connecting port.
* Caution:
Be sure to make setting so that liquid can be charged. When using a cylinder equipped with a siphon, liquid can be charged
without turning it upside down.
b) Connect the gauge manifold’s charge hose to the electronic balance’s connecting port. 3 2
c) Open the refrigerant cylinder’s valve, and, after opening the charging valve a little, close it. 1 2
d) After making zero (0) adjustment, open the charging valve and, by opening the gauge manifold’s valve Lo, charge the liquid
refrigerant. 2 5
(Before handling the electronic balance, refer to its instruction manual).
e) When the designated amount of refrigerant could not be charged, make additional charging bit by bit by cooling operation (for
the amount of each addition, follow the instruction manual prepared by the equipment manufacturer). If the first additional
charging was not enough, make the second additional charging after about one minute in the same manner as the first addi-
tional charging.
* Caution:
Be sure never to charge a large amount of liquid refrigerant at once to the unit in cooling mode, since liquid is charged from
the gas side.
Fig.6 Configuration of air purge by vacuum pump
1 Charge hose
3 Control valve (2-way)
5 Handle Lo
6 Compound pressure
gauge
Gauge manifold
8 Handle Hi (always closed)
2 Charge hose
Vacuum pump adapter
Vacuum pump
7 Service port
4 Control valve
(3-way)
-76cmHg
Caution:
Be sure to use the vacuum pump, vacuum pump adapter and
gauge manifold to refer to their instruction manuals beforehand.
Ascertain that the vacuum pump is filled with oil to the level
designated on the oil gauge.
139

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für Mitsubishi SKM20ZG-S wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Andere Handbücher von Mitsubishi SKM20ZG-S

Mitsubishi SKM20ZG-S Bedienungsanleitung - Deutsch - 24 seiten

Mitsubishi SKM20ZG-S Bedienungsanleitung - Holländisch - 24 seiten


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info