587703
24
Zoom out
Zoom in
Vorherige Seite
1/32
Nächste Seite
Add refrigerant
The equipment contains
a basic quantity of refrigerant.
Furthermore, for refrigerant line
lengths of more than 5 metres
per circuit, an additional amount
of refrigerant must be added, in
accordance with the following
chart:
ML
262
ML
352
ML
522
Basic
line length
Additional fill quan-
tity
Up to and incl.
5 m
0 g/m
5 m to max.
20 m
30
g/m
30
g/m
30
g/m
After the tightness check has
been successfully completed,
connect the vacuum pump via
the pressure gauge station to
the valve connections on the
outdoor component (see chapter
"Tightness check") and create
a vacuum.
Perform the following checks
prior to putting the unit into
operation for the first time and
after any work on the refrigeration
circuit. Record the results in the
commissioning report:
Check all refrigerant
lines and valves using
leak detection spray or soapy
water for leaks and for
inadvertent reversal of the
suction and injection lines,
with the unit at a standstill.
Check refrigerant
lines and insulation for damage.
Check electrical
connection between
indoor unit and outdoor
component
for correct polarity.
Check that all fastenings,
mountings etc.
are firm and at the correct level.
Before
Commissioning
Make sure that the refrigerant
which is used is always filled
in liquid form!
ATTENTION
NOTE
Check the refrigerant fill
quantity in the event of
overheating
Wear protective clothing when
handling refrigerant.
ATTENTION
Commissioning
Commissioning is only to be
performed and documented
by specially trained personnel.
NOTE
Once all the components have
been connected and tested, the
system can be commissioned.
A functional check should be
performed to verify its correct
function and identify any unusual
operational behaviour prior to
handing it over to the operator.
Function test and test run
Check the following points:
Leak tightness of refrigerant
lines.
Compressor and fan running
smoothly.
In cooling mode, cold air
output by the indoor unit, and
warm air output by the outdoor
component.
Functional test of the indoor
unit and all program sequences.
Check of the surface
temperature of the suction pipe
and determination of vaporiser
overheating. To measure
the temperature, hold the
thermometer to the suction
pipe and subtract the boiling
point temperature reading on
the pressure gauge from the
measured temperature.
Documentation of the
measured temperatures in the
commissioning report.
Check that the stop valves
and valve caps are tight after
carrying out any work on
the refrigerant circuit. Use
appropriate sealant products
as necessary.
NOTE
Functional test for the cooling
and heating modes
1. Remove the caps from the
valves.
2. Begin the commissioning
process by briefly opening the
shut-off valves of the external
unit until the manometer
displays a pressure of approx.
2 bar.
3. Use leak detection spray or
suitable devices to check that all
the connections are leak tight.
REMKO ML...DC - ARCTIC
24
24

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für REMKO ML522 DC wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Andere Handbücher von REMKO ML522 DC

REMKO ML522 DC Bedienungsanleitung - Deutsch - 32 seiten

REMKO ML522 DC Bedienungsanleitung - Deutsch - 32 seiten


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info