9. INSTRUCTIONS FOR COMMISSIONING PROTOCOL
FOR PELLET AND COMBI STOVES
The commissioning protocol is to be treated as a documents and
serves as the basis for the warranty and guarantee terms. It is to
be completed entirely, in particular the stove data and addresses,
the work to be performed is to be ticked off after completion. The
signatories confirm with their signatures that all the items on the list
have been concluded properly.
Note
Please return 1 completed protocol for putting into service to
RIKA Innovative Ofentechnik GmbH, Müllerviertel 20, 4563
Micheldorf, Austria.
Electrical periphery
It is important that the connection socket in the electrical periphery
is earthed. The operability of any room thermostat present must
be checked. The execution of commands is to be established by
phoning in the case of a GSM modem.
Exhaust gas system
The exhaust line, stove and combustion air inlet are part of the
combustion system as a whole; therefore the correct execution must
also be checked. The plug connections should be tight in general
since the system works with excess pressure. The exhaust tube has
a diameter of 100 mm for pellet stove, and of 150 mm for the combi
stove, which is sufficient for short distances. In the case of several
changes in direction, the resistance of the exhaust system can
increase with the flue to such an extent that the combustion quality
suffers and/or noise arises from the greater flow speed. Correct
determination of the chimney draught can only be performed at
nominal thermal output and serves to evaluate the chimney. If the
draught is more than 15 Pa, then a draught limiter should be installed.
Stove functions
These are the basic stove functions that are to be checked and
ticked off. The stove is ready for operation if these functions are
ensured.
Operator instruction
This is one of the most important points in the putting into operation.
It is very important that the operator understands the stove properly
and is prepared to assume responsibility for the basic tasks required
for operational safety.
In particular the connection between special features of a biomass
heating system and his obligations as well as the warranty and
guarantee terms must be explained. e.g. non-tested pellets and screw
blockers, lack of cleaning or maintenance and stove malfunctions.
Thorough instruction can prevent many complaints.
Stove functions
Explanation of the processes in the stove during ignition, normal
operation, cleaning phase etc.
Control
Explain operators possibilities to intervene, empty pellet container,
room thermostat, GSM modem, functions and settings, program
times if necessary. Operating instructions: Handover and reference
to the content to the following points, is a document.
Warranty terms
Difference between warranty (statutory) and guarantee (voluntary),
terms of guarantee, determination of wearing parts, reference to
pellet quality to be used and the consequences of poor quality.
Cleaning instructions
Ash and dust occurs with a biomass heating unit. The fire trough is
to be cleaned regularly with regular heating operation (in the case
of pellet operation, the drilled air holes in particular must be free
of residues). The ash drawer is to be emptied regularly. The flue
gas pipes are to be cleaned once or twice in the heating season
depending on stove type; by a specialist company is best.
Maintenance
Note
We recommend at least once a year to have all maintenance
carried out by your RIKA dealer.
Combustion
All doors must close tightly to prevent intake of false air.
17

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für Rika Interno wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Andere Handbücher von Rika Interno

Rika Interno Bedienungsanleitung - Deutsch - 20 seiten

Rika Interno Zusatzinformation - Deutsch - 36 seiten

Rika Interno Installationsanweisung - Deutsch - 44 seiten

Rika Interno Zusatzinformation - Englisch - 36 seiten

Rika Interno Installationsanweisung - Englisch - 44 seiten

Rika Interno Zusatzinformation - Holländisch - 36 seiten

Rika Interno Installationsanweisung - Holländisch - 44 seiten

Rika Interno Bedienungsanleitung - Holländisch - 20 seiten

Rika Interno Zusatzinformation - Französisch - 36 seiten

Rika Interno Installationsanweisung - Französisch - 44 seiten

Rika Interno Zusatzinformation - Italienisch - 36 seiten

Rika Interno Installationsanweisung - Italienisch - 44 seiten


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info