Boiler Installation Sequence 5
Instructions for installation and servicing aquaPLUS VUI 362-7 15
5.3 Fitting the boiler hanging bracket
Fix the hanging bracket (2) to the wall using the fixings
supplied. (it may be necessary to use additional or
alternative fixings to ensure adequate support).
Fig. 5.4: Fitting the boiler
5.4 Install the flue system
Install the flue system (refer to separate air/flue duct
installation instructions).
5.5 Fitting the boiler
• Lift the boiler (3) up to the wall so that it is slightly
above the hanging bracket (1).
• Lower the boiler slowly onto the hanging bracket so
that the slots at the rear of the boiler fully engage
onto the hanging bracket (1).
Note: If the boiler is to be fitted in a timber framed
building ensure that the bracket is secured to a
substantial part of the timber frame capable of taking
the weight of the boiler.
Note: Lift the boiler from either side at the centre of
the bottom edge.
5.6 Removing boiler casing
• Turn both securing fasteners (1) anti-clockwise by 90°
to release control panel (2).
• Pull the case (3) forward at the bottom to disengage
from the securing clips.
• Lift the case slightly to clear the top locations and
pull forward to remove.
Fig. 5.5: Remove of boiler casing