37
Step-by-step initialisation of the charging station:
1. Before the main power supply to the station is turned on, make sure that all safety
elements are turned off:
a. Socket 1 fuse switch disconnector – F3
b. Socket 1 differential protection (FID) – F5,
c. Socket 1 overcurrent protection – F6,
d. Socket 2 fuse switch disconnector – F3,
e. Socket 2 differential protection (FID) – F7,
f. Socket 2 overcurrent protection – F8,
g. Overcurrent protection of the main controller – F9.
2. Turn on the main power supply switch. Examine the casing of the station for any phase
voltage that might be present as a result of improper installation or damage caused by
the transport of the station. Check the supply voltage on the terminals. The voltage is
measured between individual phases on one side and the »ground«/»neutral« on the
other side.
3. Turn on socket 1 and socket 2 fuse switch disconnector (F3) Both energy meters (S1, S2)
should initiate at this point. If they do not initiate, contact the manufacturer's technical
support service.
4. Turn on the differential and overcurrent protection of both sockets (F5, F6, F7, F8),
5. Turn on the overcurrent protection of the main controller (F9). After the protection is
turned on, the following devices turn on as well:
a. main controller of the charging station,
b. LED display,
c. GPRS router and network switch (if installed),
d. IEC 61851 module.
6. After the controller protection is turned on, the initialisation of the main controller
begins. This process takes approximately 30 seconds. Exact duration depends on the
current state of the communication connection with a) the IEC 61851 module, b) energy
meters read modules, and c) the control centre. During initialisation of the station, the
LED display should show the message: » Please wait...«.