Commissioning
Greenstar Danesmoor Utility 2022+ and Utility System 2022+ - 6 721 846 263 (2022/01) 41
6.3 Water treatment
Ensure that the system has been cleaned. Refer to section 4.1.2 of
these instructions.
Inhibitor (Central Heating)
Check drain cocks are closed and all radiator valves are open before
adding a suitable inhibitor or combined inhibitor/anti-freeze, if the
system is exposed to freezing conditions, to the heating system
water in accordance with the manufacturers instructions.
Fill system via a WRAS approved filling loop to between 1 and 1.5
bar.
Vent all radiators; tighten vents when complete.
Re-pressurise if necessary to 1bar.
Set all controls to maximum.
Record the date when the inhibitor was added to the system in the
Boiler commissioning checklist and in the guarantee registration.
Water treatment products
Suitable water treatment products can be obtain from the following
manufacturers:
6.4 Starting the appliance
1. Check the oil supply is correctly fitted, pressure tested and in good
working order before turning on the oil supply valves to the boiler.
Turn on the main oil supply valve at the tank and draw off at least
2.5 litres of oil until a steady flow of clear uncontaminated oil can be
seen as follows:
The oil supply to the boiler should be primed before the burner is
operated to avoid unnecessary pump wear.
The use of an oil suction pump will prime and flush through any oil
supply set up simply and easily, alternatively the following
procedures can be used.
6.4.1 Single pipe gravity feed system:
Disconnect the flexible oil hose and open the isolating valve to
discharge the oil into a suitable container.
If a top entry tank has been used the pipework will need to be primed
before the oil will discharge under gravity.
When completed, close the isolating valve, reconnect the flexible oil
hose.
When the oil reaches the pump, bleed the air from the pump:
Open the isolating valve and the oil pump bleed port [1] to discharge
into a suitable container once the boiler is started up.
Switch on the electricity supply to the boiler.
Set the programmer to ON for CH and DHW.
Turn on the boiler CH control thermostat.
Allow the burner to run through to lockout .
Fig. 62
[1] Bleed and pressure gauge port
[2] Vacuum gauge connection
[3] Pressure adjuster
[4] Cover retaining screws x4
If no oil comes out of the port valve [1], then re-prime the oil line as
detailed above
Wait 2 minutes then press the lockout reset button [K].
Repeat the procedure until a steady stream of oil without air, runs
from the bleed port, then lock bleed port [1].
Switch off the boiler.
6.4.2 Double pipe sub-gravity feed systems and single pipe
suction lift with de-aerator:
Prime the oil supply pipework to prevent oil pump damage.
To prime a de-aerator [2], disconnect the flexible oil inlet hose [7]
from the isolation valve and place in a container of heating oil[6].
Connect a spare flexible oil hose [5], to discharge into container [6].
Open the isolating valve, turn on the power to the boiler and set the
programmer to ON. Prime the de-aerator until there is a steady flow
of oil into container [6]. Turn off the boiler then reconnect the
flexible oil inlet hose [7].
Turn on the boiler, set the programmer to ON and turn the room
thermostat up to create a demand for heat.
The oil level in the de-aerator will drop whilst the oil is being drawn
from the tank. If the de-aerator empties and the burner locks out
before the oil is drawn from the tank, you will have to prime the de-
aerator again.
NOTICE:
Salt based, softened water must not be used to fill
the central heating system.
The pH value of the system water must be between 6.5
and 8 or the appliance warranty will be invalidated.
NOTICE:
The concentration of inhibitor in the system should
be checked every 12 months or sooner if system
content is lost.
In cases where all attempts to find a micro leak have
failed, Worcester, Bosch Group supports the use of
Fernox F4 leak sealer.
ADEY 01242 546700 or www.adey.com
FERNOX 0330 100 7750 or www.fernox.com
SENTINEL 01928 704330 or www.sentinelprotects.com/uk
NOTICE:
Never run the appliance when the appliance/system
is unpressurised (sealed systems) or empty.
6720821683-11.1Wo
4
1
3
2
41

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für Worcester-Bosch Greenstar Danesmoor Utility Regular - Utility System wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info