3.4.2 MasterBus (optional)
The Mass Systemswitch is compatible with the MasterBus
network: a fully decentralized data network for
communication between Mastervolt devices such as the
inverter, battery charger, generator, batteries and many
more. See section 5 for details.
3.5 LOAD ON INVERTER MODE
The Short break output is transferred between the
generator input, shore input and inverter input, depending
on its availability. However, to prevent the generator from
an overload situation or to prevent the shore fuse from
tripping, the load that is connected to the Short break
output can be switched either manually or automatically
from the generator or shore power to the output of the
inverter. We call this the “load on inverter mode” or the
“force to inverter mode”.
When the load on inverter mode is switched OFF (figure
3), the Mass Systemswitch is in normal state. This means
that the Short break output is transferred between the
generator input, shore input and inverter input, depending
on the availability.
When the load on inverter mode is switched ON (figure 4),
power from the generator or the shore can no longer be
used to supply the Short break output. The Short break
output will only be supplied by the inverter. See the
manual of the remote operation panel to toggle the load on
inverter mode manually.
Figure 3: Load on inverter mode is OFF, while power from
the generator or the shore is available
Figure 4: Load on inverter mode is ON, while power from
the generator or the shore is available
3.6 AUTOMATIC LOAD ON INVERTER MODE
It is also possible to toggle the load on inverter mode
automatically. Then the load on inverter mode will be
switched ON when the current on the shore input or the
generator input exceeds a predefined set point. Then we
call it the automatic load on inverter mode” or the
automatic force to inverter mode”.
3.6.1 Traditional remote control panel
If a traditional remote control panel is applied, the
“automatic load on inverter mode” can be triggered by:
- The generator current (delayed)
- The shore current (not delayed)
To adjust the settings of the automatic load on inverter
mode refer to ADVANCED A-menu of the manual of the
remote operation panel.
3.6.2 MasterBus
If the Mass Systemswitch is controlled by MasterBus,
operation of the “automatic load on inverter mode” can be
programmed by means of an event-based command. See
section 6.3 for details. Refer to the manual of the
MasterBus remote panel for details about programming of
event-based commands.
3.6.3 Example
See figure 5. A coffee machine is switched on, causing an
extra load on the shore/generator. When the total load that
is connected to the shore or the generator exceeds its
maximum current level, first a time delay is triggered. After
this delay time the automatic load on inverter mode will be
activated: a part of the total load is switched from the
generator/ shore to the AC output of the inverter. When
the automatic load on inverter mode is activated, it is
switched off again when the adjusted time has elapsed.
Generator
or shore
Generator
or Power
Inverter
Short break
Generator
or shore
Generator
or Power
Inverter
Short break
7

Brauchen Sie Hilfe? Stellen Sie Ihre Frage.

Forenregeln

Missbrauch melden von Frage und/oder Antwort

Libble nimmt den Missbrauch seiner Dienste sehr ernst. Wir setzen uns dafür ein, derartige Missbrauchsfälle gemäß den Gesetzen Ihres Heimatlandes zu behandeln. Wenn Sie eine Meldung übermitteln, überprüfen wir Ihre Informationen und ergreifen entsprechende Maßnahmen. Wir melden uns nur dann wieder bei Ihnen, wenn wir weitere Einzelheiten wissen müssen oder weitere Informationen für Sie haben.

Art des Missbrauchs:

Zum Beispiel antisemitische Inhalte, rassistische Inhalte oder Material, das zu einer Gewalttat führen könnte.

Beispielsweise eine Kreditkartennummer, persönliche Identifikationsnummer oder unveröffentlichte Privatadresse. Beachten Sie, dass E-Mail-Adressen und der vollständige Name nicht als private Informationen angesehen werden.

Forenregeln

Um zu sinnvolle Fragen zu kommen halten Sie sich bitte an folgende Spielregeln:

Neu registrieren

Registrieren auf E - Mails für Mastervolt Mass Systemswitch 16 kW wenn:


Sie erhalten eine E-Mail, um sich für eine oder beide Optionen anzumelden.


Das Handbuch wird per E-Mail gesendet. Überprüfen Sie ihre E-Mail.

Wenn Sie innerhalb von 15 Minuten keine E-Mail mit dem Handbuch erhalten haben, kann es sein, dass Sie eine falsche E-Mail-Adresse eingegeben haben oder dass Ihr ISP eine maximale Größe eingestellt hat, um E-Mails zu erhalten, die kleiner als die Größe des Handbuchs sind.

Ihre Frage wurde zu diesem Forum hinzugefügt

Möchten Sie eine E-Mail erhalten, wenn neue Antworten und Fragen veröffentlicht werden? Geben Sie bitte Ihre Email-Adresse ein.



Info